12 men cement a wall in 18 days if 8 men do the same work how do long will it take to complete the work
Answers
Answered by
12
Answer:
Step-by-step explanation:
12 take 18 days
this implies 1 will take 12 x 18
then 8 will take (12 x 18)/8 =27 days