12 men complete a certain work in 20 days, then the same work are be completed in how many days by 15 men ?

Answers

Answered by jinadevkv
1

12 men can complete the work in 20 days.

So, total work = 12*20 = 240

Time required for 15 men to complete = 240/15 = 16 days