Math, asked by nelsonjacob, 1 year ago

12 men complete a work in 9 days. After
they have worked for 6 days, 6 more men
join them. How many days will they take to
complete the remaining work?​

Answers

Answered by ayushgarg15
1

1 day more to complete the work

Answer

Answered by vansh81111c
6

Answer:

2 days

Step-by-step explanation:

12 men worked for 9 days=12*9=108

after working for 6 day12*6=72

days left=108-72=36

6 more men joined=12+6=18

so,no. of days taken=36/18=2 days