12 men complete a work in 9 days. After they
have worked for 6 days, 6 more men join
them. How many days will they take to
complete the remaining work?
(a) 2 days
(b) 3 days
(c) 4 days
(d) 5 days
(e) None of these
Answers
Answered by
1
Answer:
(a) 2 days
Step-by-step explanation:
In 1 day, 12 men will complete 1/9 of work.
In 6 days 12 men will complete 6/9=2/3 of work.
So,
after 6 days the work left is 1/3.
°•° 12 men will complete the 1/3 work in 3 days
So,
1 man will complete 1/3 of the work in 36 days.
18 men (12+6) will complete the remaining work in
36/18= 2 days is the answer.
Hope this helps you.
Mark me as brainliest.
Answered by
2
Answer:
2 days
Step-by-step explanation:
12 men worked for 9 days = 12×9 = 108
after working for 6 days = 12×6 = 72
days left = 108 - 72 = 36
6 men more joined = 12+6 =18
so, no. of days taken to complete the remaining work = 36/18 = 2 days
hope this will help u.
Similar questions
Math,
5 months ago
Social Sciences,
5 months ago
Math,
5 months ago
Math,
11 months ago
Biology,
11 months ago
Science,
1 year ago
English,
1 year ago
Accountancy,
1 year ago