12 men complete a work in 9 days, after they have worked for 6 days, 6 more men join them, how many days will they take to complete the remaining work? ​

Answers

Answered by subhakunnath1980
0

Answer:

Step-by-step explanation:

2 men worked for 9 days = 12 * 9 = 108

after working for 6 days = 12 *6 = 72

days left = 108 - 72 = 36

6 more men joined = 12 + 6 = 18

so, no. of days taken = 36 / 18 = 2 days