Math, asked by shritesh333korde, 5 months ago

12 men complete a work in 9 days. After they worked for 6 days, 6 more men join them. How many days will they took to complete the remaining work?
1. 3
2. 4
3. 5
4. 2
5. non of these​

Answers

Answered by phanee19
0

Answer:

didi Izzo Yahoo Tajuddin Shishir so

Answered by rajasrinivasarao45
1

Answer:

Hope it helps u... (4)

Mark me as brainliest...!!!

Step-by-step explanation:

In 1 day, 12 men can complete 1/9 of work

In 6 days, 12 men will complete 6/9 = 2/3 of work

So, after 6 days the work left is 1/3

Therefore , 12 men can complete the 1/3 work in 3 days

So, 1 men will complete 1/3 of the work in 36 days

There 18 men (12+6) will complete the remaining work in 36/18 = 2 days

OPTION - (4)

Similar questions