12 men complete a work in 9 days. After they worked for 6 days, 6 more men join them. How many days will they took to complete the remaining work?
1. 3
2. 4
3. 5
4. 2
5. non of these
Answers
Answered by
0
Answer:
didi Izzo Yahoo Tajuddin Shishir so
Answered by
1
Answer:
Hope it helps u... (4)
Mark me as brainliest...!!!
Step-by-step explanation:
In 1 day, 12 men can complete 1/9 of work
In 6 days, 12 men will complete 6/9 = 2/3 of work
So, after 6 days the work left is 1/3
Therefore , 12 men can complete the 1/3 work in 3 days
So, 1 men will complete 1/3 of the work in 36 days
There 18 men (12+6) will complete the remaining work in 36/18 = 2 days
OPTION - (4)
Similar questions
Social Sciences,
2 months ago
Math,
2 months ago
Math,
2 months ago
English,
5 months ago
Math,
10 months ago