12 men complete one - third of the work in 8 days than in how many days 16 men will complete that work
Answers
Answered by
1
12 men can complete 1/3rd of the work in 8 days.
So, 12 men can complete the whole work in 8×3= 24 days.
∴ 1 man can complete the work in 24× 12= 288 days
16 men can complete the whole work in 288/16 = 18 days