12 men complete the 2400 sq.M ploughing work in 10 days how many men are required to complete 3600 sq.M ploughing work in 18 days

Answers

Answered by xItzKhushix
6

Answer:

\bf{\huge{\underline{\boxed{\tt{\blue{Answer:-}}}}}}

2400 sq m takes 12*10 = 120 man-days

=> 1 man-day = 20 sq meters

3600/20 = 180 man-days

180 man-days/18 days = 10 men

\boxed{10 \:men\: are \:required}