12 men do one piece work in 21 days. same work in 1 day how many men will be needed
Answers
Answered by
0
Answer:
42 men
Step-by-step explanation:
1 day = 24hours
21÷12
1.75
1.75 × 24 hour
42
so 42 men will be needed to complete the work..
Answered by
1
Answer:
12 men = 21 days
1 man = 252 days
1 man in 1 day = 1/252 of the work
6 men = 6/252 = 1/42 of the work
15 women = 21 days
1 woman = 315 days
1 woman in 1 day =1/315 of the work
10 women in 1 day = 10/315 = 2/63 of the work
so 6men + 10 women in 1 day = 1/42 +2/63 = 7/126= 1/18
ANSWER 18 days
Step-by-step explanation:
that is the answer army
hope you have a nice day