12 Men finish a piece of work in 10 days working 8 hours daily how many men are ruquired to finish the same work in 8 days working 15 hours ?
Attachments:
Answers
Answered by
1
You have to just follow a simple concept-
M1×D1×H1= M2×D2×H2
Where M is no. of Men, D is no. of days and H is for Hours.
Now put all the given values in the above formula
12×10×8=M2×8×15
M2=8 Men