12 men or 15 women can do a piece of work in 21
days. Find the number of days required to complete
the same work by 6 men and 10 women.
(a) 15
(b) 18
(c) 21
(d) 24
(
Answers
Answer:
6 men and 10 women can complete in 15 days
Step-by-step explanation:
- 12 men or 15 women can do a piece of work in 21 days
- Number of days required to complete the same work by 6 men and 10 women
Given that , 12 men or 15 women can do a piece of work in 21 days
➜ i.e 12 men = 15 women
⟮ Dividing above by 12 to get one man's work in term of women ⟯
➜
➜
⟮ Multiplying above equation by 6 to get 6 men work in term of women ⟯
➜
➜ ⚊⚊⚊⚊ ⓵
➜ 6 men + 10 women ⚊⚊⚊⚊ ⓶
⟮ Putting the values of 6 men from ⓵ to ⓶ ⟯
➜ 6 men + 10 women
➜
➜ ⚊⚊⚊⚊ ⓷
Given that 15 women can finish the work in 21 days
Clearly days and women are in inverse relation
i.e If the number of women are increased then the days required to finish the work will decrease
- Let 1 women can finish the work in "x" days
So,
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
➜ 15 × 21 = x × 1
➜ x = 315 ⚊⚊⚊⚊ ⓸
- Hence 1 women can finish the work in 315 days
From ⓷
⚊⚊⚊⚊ (z)
Here also days and women are in inverse relation
From ⓸ we got that 1 women can finish the work in 315 days
So,
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
➜
➜
➜
➜ y = 9 × 2
➨ y = 18
Thus ,
- Hence 6 men and 10 women can finish the work in 18 days
∴ Option (b) 18 is correct