Math, asked by rajesh383, 1 year ago

12 men or 15 women can finish a work in 24 days in how many days the same worker can be finished 8 men and 8 women​

Answers

Answered by khushi762005
3

12 men= 15 women

1 women = 15 / 12 women

8 men = 15 / 12 × 8

solve this equation

now add in 8 women

number of women / number of days