12 men or 18 women can do a piece of work in 14 days how many days will 8 men and 16 women take to complete the work
Answers
Answered by
1
9 days
mark it as brainliest
Answered by
0
Answer: 21 days
Step-by-step explanation: Hence we will answer the question by taking men.
12 men can do a piece of work in days = 14 days
So, 1 man can do a piece of work in days = 12*14 = 168days
Therefore 8 men can do the work in days = 168/8 = 21 days.