Math, asked by vidisha2956, 9 months ago

12 men take 18 days to construct a road find the number of days 9 men take to construct the same road​

Answers

Answered by Anonymous
29

Step-by-step explanation:

M(1)*D(1) = M(2)*D(2)

12 * 18 = 9 * D(2)

D(2) = 12*2 = 24 days

Answered by bhavu1435
9

Answer:

12. 18

9 ?

9 multiply by 18 = 162

Similar questions