12 men working 8 hours a day can complete a task in 16 days. If the same task must
be completed in 8 days only, how many more people would be required if all of them
work for 12 hours a day?​

Answers

Answered by akankshakamble6
1

Answer:

answer is 16

hope will be helpful!!