12 men working 8 hours a day complete a piece of work in 10 days to complete the same work in 8 days working 15 hours a day how many men are needed
Answers
Answered by
0
Answer:
8 men
Step-by-step explanation:
P1H1D1=P2H2D2
(12*8*10)=P2(8*15)
960= P2(120)
Then P2= 960/120
P2=8
Answered by
0
Answer:
Step-by-step explanation:
For first case,
No. of men= 12
work done daily= 8 hrs
Days required to complete= 10 days
Total hours men worked= work done daily*total days required= 8*10=80 hrs
For Second case,
No. of men be 'x'.
work done daily= 15 hrs
Days required to complete= 8 fays
Total hours men worked= work done daily*total days required= 15*8=120 hrs
So, we can write:
⇒12/80=x/120
⇒12*120=80*x
⇒12*120/80=x
⇒12*3/2=x
⇒6*3=x
⇒x=18
Therefore, no. of men needed = 18
Please leave a heart if this helped you. :)