12 men, working 8 hours a day, complete a piece of work in 10 days. To complete the same work in 8 days, working 15 hours a day, the number of men required,is
Answers
Answered by
2
Answer:
8
Step-by-step explanation:
12 x 8 x 10 = m x 15 x 8
960 = m x 120
960/120 = m
8 = m