12 men, working 8 hours a day, complete a piece of work in 10 days. To complete the same work in 8 days, working 15 hours a day, the number of men required,is

Answers

Answered by khushibhargava1905
2

Answer:

8

Step-by-step explanation:

12 x 8 x 10 = m x 15 x 8

960 = m x 120

960/120 = m

8 = m