Math, asked by putti2, 1 year ago

12 men working at 6 hours per day can do a piece of work in 14 days . how many workers can complete the same work in 8.days working at 7 hours per day ?

Answers

Answered by shubhamjoshi033
9

Answer:

18 workers can complete the same work in 8 days working at 7 hours per day

Step-by-step explanation:

Given 12 men working at 6 hours per day can do a piece of work in 14 days

=> Number of man hour days = 12 x 6 x 14 = 1008

Let n number of workers work for 8 days at 7 hours per day to complete the work

=> Number of man hour days = n x 8 x 7 = 56n

These man hour days should be same in both the cases,

=> 56n = 1008

=> n = 1008/56 = 18

Hence 18 workers can complete the same work in 8 days working at 7 hours per day

Answered by amitnrw
6

Answer:

18 workers will be required

Step-by-step explanation:

12 men working at 6 hours per day can do a piece of work in 14 days

Total hrs required to complete work = 12 * 6 * 14 = 1008 hrs

Total hrs in 8 day at 7 hrs per day by 1 worker = 8 * 7 = 56 hrs

Number of workers required = Total hrs/ Hrs by 1 worker

= 1008/56

= 18

18 workers will be required