: 12 painters can paint a wall of 180 m long in 3 days. How many painters are
required to paint 200 m long wall in 5 days?
oll and inversely
Answers
Answered by
2
Answer:
8
Step-by-step explanation:
180m can be completed in 3 days by 12 painters
so in 1 day 180/3(12) m is completed
=5
so 5m is completed in 1 day
so the number of painters required is
200/25=8
Answered by
3
Answer:
8
Step-by-step explanation:
12 painters paint 180 m wall in 3 days
Work done in one day = 180/36.
=5
Painters needed = 200/ 25
= 8 painters