12 painters can paint a wall of 180 m long in 3 days . How many painters are requird to paint 200 m long wall in 5 days ?
Answers
Answered by
14
180/12*3=5
1painter 1day me 5m wall paint karega
isliye 200m wall paint krne me 200/5*5=8 painter
Answered by
11
Answer:
8
Step-by-step explanation:
180m can be completed in 3 days by 12 painters
so in 1 day 180/3(12) m is completed
=5
so 5m is completed in 1 day
so the number of painters required is
200/25=8