12 painters can paint at 8 hours of 180 meters long in in three days how many painters are required to paint 200. meters long wall i 5 fays​

Answers

Answered by shettysulaksha75
2

pls mark me as brainliest

Attachments:
Answered by laharilaharis
0

Answer:

8 men required

Step-by-step explanation:

1day paint work done 180/3= 60 meters paint done

1man paint work done in 1day = 60/12=5meters paint work done

1 day work done in 5days for 200m =200/5=40m

work done by 1day = 40/5=8men