12 person can finish the piece of work in 15 days.In how many days will the same work be completed by 20 person?​

Answers

Answered by Jyotu1972
1

Answer:

25 days

Step-by-step explanation:

no. of days of work completed by 12 persons =

15 days

no. of days of work completed by 20 persons =

let the no. of days be x

12/15 = 20/x

= 12x = 15 × 20

x = 15 ×20/12

= 5× 5

= 25

x = 25

so, the number of days are 25

please mark me as brainliest...please


sanjeevkumar94468: Thank you
Jyotu1972: welcome