12 Persona can finish work in 15 days in how many days in how many days will the same work be complete with 20 person
Answers
Answered by
1
Answer:
9 Days
Step-by-step explanation:
This question is based on Indirect Proportion
xy = k
Where x and y are variables but k is constant
12 persons can finish the work in 15 days. Here :
x = 12
y = 15
k = xy
k = 12 × 15
k = 180
'in how many days will the same work be complete with 20 person ?' Here :
x = 20
(k is always constant so)
k = 180
y = ?
Let y = a days. Then the equation will be :
xy = k
20 × a = 180
a = 180/20 = 9
a = 9 days
Hence, 20 persons will finish the work in 9 days