12 persons can complete the work in 18 days. after working for 6 days, 4 more persons added to complete the work fast. in how many more days they will complete the work? 1) 9 2) 8 3) 7 4) 10
Answers
Answered by
5
( 12 × 18 ) - ( 12 × 6 )
= 216 - 72 = 144
144 ÷ ( 12 + 4 )
= 144/16
= 9 days
= 216 - 72 = 144
144 ÷ ( 12 + 4 )
= 144/16
= 9 days
Answered by
5
Answer:
9 days.
Step-by-step explanation:
Twelve men can complete a work in 18 days.
12 men 1 day work =
12 men 6 days work =
Remaining work =
After 6 days 4 more men joined them.
1 men 1 day work =
16 men 1 day work =
=
So, 16 men complete part of work in days = 1
16 men complete whole work in days =
16 men complete part of work in days:
=
=
So, they will take 9 days more altogether to complete the work .