Math, asked by ManjunathHeman, 1 year ago

12 students can do a job in 10 days, but on the starting day, two of them informed that they are not coming, by what fraction will the number of days required for doing the whole work get increased?
a)4/5
b)3/8
c)3/4
d)1/5​

Answers

Answered by TheLostMonk
4

Answer:

let the required days be 'x'

Step-by-step explanation:

original strength = 12

New strength = 12-2 = 10

12 × 10 = 10 × x

x = 12 days

days increased = 12-10 = 2 days

in fraction = 2/10 = 1/5 Answer

Option (d) is correct