Economy, asked by bh7hospitality, 7 months ago

12 Tasks to 4 Workers

Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There exists unlimited demand unless stated otherwise.

Time to Complete Task (seconds):

Task 1: 30
Task 2: 25
Task 3: 15
Task 4: 20
Task 5: 15
Task 6: 20
Task 7: 50
Task 8: 15
Task 9: 20
Task 10: 25
Task 11: 15
Task 12: 20
The current conveyor-paced assembly-line configuration assigns the workers in the following way:

• Worker 1: Tasks 1, 2, 3

• Worker 2: Tasks 4, 5, 6

• Worker 3: Tasks 7, 8, 9

• Worker 4: Tasks 10, 11, 12

Assume a demand rate of 20 units per minute. What would be the takt time of the process (in seconds per unit)?

Answers

Answered by DakshHedau
0

Answer:

3 task to each person...

Answered by jebaliyarushiraj
3

Explanation:

worker task 456........