12 women can complete a work in 36 days. 18 men in 60 days. 8 men and 20 men work for 20 days. If only men were to comply the work in 4 days. How many men would be required
Answers
Answered by
8
12 men in 36 days can do a work.
1 man in a day can do 112×36 work.
8 men in 20 days can do 8×2012×36=1027 work.
Similarly, we find that 20 women in 20 days can do 1027work.
Remaining work =727
Now, because in 60 days a work is done by 20 women.
In 1 day a work done by 20×60 women.
In 4 days 727 work is done by 20×60×727×4= 70 women.
1 man in a day can do 112×36 work.
8 men in 20 days can do 8×2012×36=1027 work.
Similarly, we find that 20 women in 20 days can do 1027work.
Remaining work =727
Now, because in 60 days a work is done by 20 women.
In 1 day a work done by 20×60 women.
In 4 days 727 work is done by 20×60×727×4= 70 women.
asp3865:
hi
Answered by
1
12 men can complete a piece of work in 36 days
=> 1 man can complete the work in 36 × 12 days (∵ less man, more days. inversely proportional)
=> Work done by 1 man in 1 day = 136×12136×12
18 women can complete the same piece of work in 60 days
> 1 woman can complete the work in 60 × 18 days
=> Work done by 1 woman in 1 day = 160×18160×18
Work done by 8 men and 20 women in 1 day = 836×12+2060×18=154+154=127836×12+2060×18=154+154=127
Work done by 8 men and 20 women in 20 days = 20272027
Remaining work = 1−20271−2027 = 7
Let n women complete this work in 4 days. Then
160×18×n×4=727n15×18=727n=15×18×727=15×2×73=5×2×7=70160×18×n×4=727n15×18=727n=15×18×727=15×2×73=5×2×7=70
=> 1 man can complete the work in 36 × 12 days (∵ less man, more days. inversely proportional)
=> Work done by 1 man in 1 day = 136×12136×12
18 women can complete the same piece of work in 60 days
> 1 woman can complete the work in 60 × 18 days
=> Work done by 1 woman in 1 day = 160×18160×18
Work done by 8 men and 20 women in 1 day = 836×12+2060×18=154+154=127836×12+2060×18=154+154=127
Work done by 8 men and 20 women in 20 days = 20272027
Remaining work = 1−20271−2027 = 7
Let n women complete this work in 4 days. Then
160×18×n×4=727n15×18=727n=15×18×727=15×2×73=5×2×7=70160×18×n×4=727n15×18=727n=15×18×727=15×2×73=5×2×7=70