12 workers can build a wall in 60 days. If they work for 20 days and 8 new more workers
employed. If new workers can do the same work in 40 days. Then find the total days to
complete the whole work.
Answers
Answered by
3
Answer:
The total days to complete the whole work is 24 days .
Step-by-step explanation:
Given as :
Number of days required by 12 workers can build a wall = 60 days
∴ Number of days required by 1 worker can build a wall = 12 × 60 = 720 days
i.e Less men = more days
∴ 1 worker's 1 day's work =
Part of work done in first 20 days = =
Now, Left part of work = 1 - =
Or, Left part of work =
Now, As = constant
So, =
or, =
Or, 12 × 20 × 2 = 20 × d
Or, 480 = 20 d
∴ d =
i.e d = 24
Hence, The total days to complete the whole work is 24 days . Answer
Answered by
0
Answer:
Answer is 24 days.
Step-by-step explanation:
24 days
Similar questions