Math, asked by vikashtiwari965, 1 year ago


12 workers can build a wall in 60 days. If they work for 20 days and 8 new more workers
employed. If new workers can do the same work in 40 days. Then find the total days to
complete the whole work.​

Answers

Answered by sanjeevk28012
3

Answer:

The total days to complete the whole work is 24 days .

Step-by-step explanation:

Given as :

Number of days required by 12 workers can build a wall = 60 days

∴ Number of days required by 1 worker can build a wall = 12 × 60 = 720 days

i.e Less men = more days

∴ 1 worker's 1 day's work = \dfrac{1}{720}

Part of work done in first 20 days = \dfrac{20}{60} = \dfrac{1}{3}

Now, Left part of work = 1 - \dfrac{1}{3} = \dfrac{3 - 1}{3}

Or, Left part of work = \dfrac{2}{3}

Now, As \dfrac{men\times day}{work} = constant

So,  \dfrac{m_1\times d_1}{w_1} = \dfrac{m_2\times d_2}{w_2}

or, \dfrac{12\times 20}{\frac{1}{3}}   = \dfrac{20\times d}{\frac{2}{3}}

Or, 12 × 20 × 2 = 20 × d

Or, 480 = 20 d

∴  d = \dfrac{480}{20}

i.e  d = 24

Hence, The total days to complete the whole work is 24 days . Answer

Answered by yugansverma12
0

Answer:

Answer is 24 days.

Step-by-step explanation:

24 days

Similar questions