12 workers can complete a piece of work in 10 days. If the number of workers are reduced 1/3 of the original number. then how many more days would be required to complete the same work?
Answers
Answered by
10
Answer:
Your answer is here:-
Step-by-step explanation:
We have been given that 12 workers can complete a piece of work in 10 days.
Also, that the number of workers is reduced to 1/3.
We know that if the workforce is reduced then the time will increase.
Now, 1/3rd of original no. of workers =1/3×12=4.
It is a case of inverse variation as we know,
So, 12 workers can complete a work in 10 days
Therefore, 4 workers can complete the same work in 12×104=1204=30 (Because work remains same)
Hence, the number of extra days that will be required by a smaller number of workforces will be =(30−10)=20.
Hope it helps you.
Similar questions
Hindi,
16 days ago
Math,
16 days ago
World Languages,
1 month ago
English,
1 month ago
Science,
9 months ago