12 workers can complete a task in 9 days. If the task has to be completed in 3 days lesser, how many more men will be required?​

Answers

Answered by ElenaSam
0

Answer:

18 workers

Step-by-step explanation:

Original measured work content = 12 men x 9 days = total work content of 108 days

Revised Work schedule 12 men x 6 days = 72 days work completed with a balance of 36 days, but now divided by 18 workers instead of 12