Math, asked by noyanglama1, 3 months ago

12 workers can do a piece of work in 10 days. how many workers should be added to complete the work in 16 days? process wise urgent.

Answers

Answered by OoExtrovertoO
1

Answer:

12 workers can do a piece of work in 20 days. How many workers should be added to complete the work in 16 days?

The work requires the input of

12 *20 = 240 worker-days

So if you wish to complete the work in 16 days you will require a total of 240 worker-days / 16 days = 15 workers.

Since you already have 12 workers, you should add 3 more workmen.