Math, asked by noyanglama1, 1 month ago

12 workers can do a piece of work in 10 days. how many workers should be added to complete the work in 16 days? process wise urgent.

Answers

Answered by pranavsuhas9
0
Answer - 19.2 which is 19 workers
Answered by catalyzingsuccess
0

just think

if 12 workers can complete work in 10 days then if the time is increased by 6 days the no of workers needed would be less

pls check you question

I think the question is incomplete

Similar questions