12 workers can do a piece of work in 16 days. if 12 more workers are added to the work force in how many days will they complete the works?
Answers
Answered by
10
☆Hey Mate!!!☆
Days needed to do 1 part by 12 workers = 16
Days needed to do 1 part by 1 worker = 16 × 12
Days needed to do 1 art by 24 ( 12 + 12 ) =
16 × 12 × 1/ 24 = 16/2 = 8 days
Hope it helps☺!
Days needed to do 1 part by 12 workers = 16
Days needed to do 1 part by 1 worker = 16 × 12
Days needed to do 1 art by 24 ( 12 + 12 ) =
16 × 12 × 1/ 24 = 16/2 = 8 days
Hope it helps☺!