12 workers were employed to complete the construction of a building in 60 days. how many additional numbers of workers should be employed to complete the construction in 45 days ?
Answers
Answered by
9
Answer:
12 × 60 ÷ 45 = 16
16 is the correct answer.
please mark me brainliest ❤❤❤❤❤❤❤
Answered by
1
Answer:
3 worker
Step-by-step explanation:
(60-45)days= 15
15-12= 3 hence 3 worker shall be employed to complete work in 45 days (this answer is right verified by my text book) pls write it with more language