120 men can complete a work in 200 days. After 5 days 30 men left. In how many days will the work be completed?

Answers

Answered by Guramrit0810
1
Total provision can be consumed by 1 men =120×200=24000
Since after 5 days 30 men left
Total provision consumed in 5 days= 120×5=600 men
Total provision left= 24000-600=23400
Total men left after 5 days 120-30=90
In how many days =23400/90=260 days