120 men can finish a work in 200 days. After 5 days, 30 men left the work now in how many days the work will be completed
Answers
Answered by
12
HEY ❤️ ❤️
Provision available for 120 men for 200 days .
total provision can be consumed by 1 man = 120 × 200 = 24000 days .
Since , after 5 days 30 men died
Total provision consumed in 5 days= 120 × 5 = 600 men days
total provision left = 24000 - 600 = 23400 men days
Persons left after 5days = 120 - 30 = 90 men
No of days it can last for remaining people
Thus, the remaining provision will last for 260 days.
Provision available for 120 men for 200 days .
total provision can be consumed by 1 man = 120 × 200 = 24000 days .
Since , after 5 days 30 men died
Total provision consumed in 5 days= 120 × 5 = 600 men days
total provision left = 24000 - 600 = 23400 men days
Persons left after 5days = 120 - 30 = 90 men
No of days it can last for remaining people
Thus, the remaining provision will last for 260 days.
ayush9151:
thanks
Answered by
3
Answer:
260 days will be the ans pls pls pls mark me as brainlist
Similar questions
Chemistry,
6 months ago
India Languages,
6 months ago
Geography,
6 months ago
Math,
1 year ago
Math,
1 year ago