120 men dig tunnel in 180 days how many man complete this task in 150 days
Answers
Answered by
0
Answer:
100 men
Step-by-step explanation:
first 1 day ka nikalo
next 150
Answered by
0
Answer:
144 men
Step-by-step explanation:
let work done by one man be 'a'
then work done by 120 men = 120a
120a takes 180 days
total work = 120a x 180 = 21600a
let the no of men who complete the task in 150 days be 'x'
150ax = total work
so 21600a = 150ax
150x = 21600
15x = 2160
x = 2160/15 = 144 men