120 men working 9 hours a day can construct a road in 40 days . how long would it take to construct the same road if 150 men work 6 hours a day on it?


Answers

Answered by Anonymous
27

<font color=red><marquee behavior=alternate>Solution</marquee></font>

it would take

 = 40 \times  \frac{9}{6}  \times  \frac{120}{150}  \\  = 48 \: days

Answered by pushpa15284
5

1 man will complete the job in 16×12 days.

1 man will complete the job in 16×12 days.So, 4 will do in

1 man will complete the job in 16×12 days.So, 4 will do in 4

1 man will complete the job in 16×12 days.So, 4 will do in 412×16

1 man will complete the job in 16×12 days.So, 4 will do in 412×16

1 man will complete the job in 16×12 days.So, 4 will do in 412×16 =48 days.

1 man will complete the job in 16×12 days.So, 4 will do in 412×16 =48 days.Hence, option D is the correct answer