120 people can complete a piece of work in 30 days in how many days can 150 people with
Answers
Answered by
0
120 people can do work in 30days
Now in Question
150 people can do work in how many days
120 people - 30 days
150 people - ? (X)
Now cross multiply
120 multiply x is equal to 150 multiply 30
Therefore
X is equal to 150 multiply 30 divided by 120
4500 divided by 120
Therefore answer is 37.5