Math, asked by yadavsurender064, 1 year ago

120 persons can dig a well 60 days after they have worked for 50 days how many more persons work the complete in 30days​

Answers

Answered by ayanhussain192837465
0

Answer:

240 persons

Step-by-step explanation:

Answered by VenzlaChaurasia
0

Answer:

let the number of persons be x.

Through method of indirect variation:-

No. of persons. 120. x

No. of days. 110(50+60.) 30

ATQ;

120*110=30x

So, the answer is x=440 persons