120 persons can dig a well in 60 days. After they
have worked for 15 days, how many more persons
should be employed so as to complete the work in
another 30 days?
+please answer quickly... you are my final hope
Answers
Answered by
0
Explanation:
let the number of persons be x.
Through method of indirect variation:-
No. of persons. 120. x
No. of days. 110(50+60.) 30
ATQ;
120*110=30x
So, the answer is x=440 persons