122 men build a railway tunnel in 72 days how many more men need to do it in 48 days
Attachments:
Answers
Answered by
6
Answer:
168 men
112*72/48= 168 men
verification
112*72= 168*48
8064=8064
LHS = RHS
168 MEN CAN FINISH WORK IN 48 DAYS.