12men can do a piece of work in 15 days . How long will ten men take do the same work​

Answers

Answered by listonfdo
2

18

Step-by-step explanation:

let x be the number of days

12m * 15d = 10m * x

(12m = 12 men , 15d =15days , 10m = 10 men )

12 * 15 = 10 * x

x = 180 / 10= 18 days.

Hope this helps you.

Answered by shuchisthakkar29
0

Answer:

12/10 = 1.2

Therefore 12 men is 1.2 times as efficient as 10 men.

Thus divide 15 by 1.2.

15/1.2. = 12.5 Days

The reason we divide is:

Imagine that it is 2 times as efficient, then by logic it would take half the time, i.e. Divide by 2 = Multiply by 1/2