12workers take4hours to completeal a job. how long would it take 15workers to complete the job
Answers
Answered by
0
Answer:
12. 4
15. x
where x is answer
using indirect proportionality
15/12=4/x
5/4=4/x
4/5=x/4
16/5 hrs
3.1 hrs
Answered by
1
Here
workers and time are in indirect proportion.
x1y1=x2y2
here
x1=12
y1=4
x2=15
y2=x
12×4=15×x
x=12×4/15
=3.2hours
time taken by 15 workers to complete work is 3.2hours.
I think this is helpful to someone. Please thank me and follow me. And add me to brainliest please.