13. 64 men working 8 hours a day plan to complete a plece
of work in 9 days. However 5 days later they find that
they had completed only 40% of the work. They now
wanted to finish the remaining portion of the work in 4
more days. Find the number of hours per day that they
need to work in order to achieve the target.
and Fcan complete a
C​

Answers

Answered by hanshu9
1

Answer:

I not know this anwer please tell any buddy

Answered by amitnrw
0

Given  : 64 men working 8 hours a day plan to complete a piece of work in 9 days.

5 days later they find that they had completed only 40% of the work.

They now wanted to finish the remaining portion of the work in 4 more days.

To Find  : the number of hours per day that they need to work in order to achieve the target.

Solution:

64 men working 8 hours a day for 5 days

Hence Work done = 64 * 8 * 5 = 64  * 40  hrs

Let say total Work = W hrs

Work Done = 40 % of the work

(40/100) W  = 64 * 40

=> W = 64 * 100  hrs

Remaining  Work  = 64 * 100 - 64 * 40

= 64 * 60  hrs

Remaining days = 4

Work done in a hr = H

Men = 64

Hence Work Done = 64 * 4 * H   hrs

64 * 4 * H  =  64 * 60

=> 4 * H = 60

=> H = 15

They need to work 15 hrs per day in order to achieve the target.

Learn More:

20 men can complete a piece of work in 15 days. One man starts the ...

brainly.in/question/9066294

A work is completed such that on the nth day from the start n men ...

brainly.in/question/11508647

Similar questions