13. A and B can do a job in 6 days, B and C in 9 days, and A and C in 12 days. How much time will they take to complete the job if they all work together? How long will each of them take to do the job? the ci
Answers
Answered by
0
Answer:
a rhi spokeswoman said that they were not allowed to be identified by the police act as per their decision
Answered by
4
Step-by-step explanation:
Let us give the job a value of 1.
A and B require 6 days to finish the job
⇒A and B finish \frac{1}{6}
6
1
of the job in 1 day.
A + B = \frac{1}{6}
6
1
Similarly we can say that,
B + C = \frac{1}{9}
9
1
and
A + C = \frac{1}{12}
12
1
Adding all of these,
A + B + B + C + C + A = \frac{1}{6}
6
1
+ \frac{1}{9}
9
1
+\frac{1}{12}
12
1
2A + 2B + 2C = \frac{6+4+3}{36}
36
6+4+3
2(A + B + C) = \frac{13}{36}
36
13
A + B + C = \frac{13}{72}
72
13
Therefore, they can complete the work in \frac{72}{13}
13
72
days
Similar questions