13. A and B can do a piece of work in 20 days, B and C in 30 days and C and A in 36 days.
(i) How much time will it take to finish the work together?
(ii) In how many days, will each finish the work alone?
it answer should be
18 days
45,36,180 days
Answers
Step-by-step explanation:
A+ B can do a work in 20 days.
therefore in 1 day they complete 1/20th work
B+ C can do a work in 30 days.
therefore in 1 day they complete 1/30th work
C+ A can do a work in 36 days.
therefore in 1 day they complete 1/36th work
i) if they work together in one day they will complete
(A+B)+(B+C)+(C+A) = (1/20) + (1/30) + (1/36)
➡2A +2B + 2C = (1/20) + (1/30) + (1/36)
➡2(A+B+C) = (27+18+15)/ 540 { here we took 2 as common and also 540 is the LCM of 20,30&36}
➡2(A+B+C) = 60/540
➡2(A+B+C) = 1/9
➡A+B+C = 1/(9×2)
➡A+B+C = 1/18
since they together complete 1/18 th of the work in one day so they will need 18 days to complete the work.
ii) A+ B+ C = 1/18
➡A + (B+C) = 1/18
➡A + 1/30 = 1/18
➡A = (1/18) - (1/30)
➡A = (5-3)/ 90 {here we took LCM of 18 & 30}
➡A = 2/90
➡A =1/45
Since A complete 1/45th of the work in one day so A will complete tge whole work in 45 days.
similarly ,
A+B+C =1/18
➡B + (C+A) = 1/18
➡B + 1/36 = 1/18
➡B = (1/18) - (1/36)
➡B = (2-1)/36
➡B = 1/36
so B will complete the work in 36 days.
A+B+C =1/18
➡C + (A+B) = 1/18
➡C + 1/20 = 1/18
➡C = (1/18) - (1/20)
➡C = (10-9)/180
➡C = 1/180
So C will complete the work in 180 days