13. If 52 men can do a piece of work in 35 days, in how many men will do it in 14 days
? don't paste from webs
Answers
Answered by
1
Answer: 130 men
Step-by-step explanation:
In 35 days a piece of work can be done by 52 men.
In 1 day a piece of work can be done by 52* 35 = 1820 men
In 14 days a piece of work can be done by 1820/14 = 130 men
Answered by
0
In 35 days a piece of work can be done by 52 men.
In 1 day a piece of work can be done by 52* 35 1820 men
In 14 days a piece of work can be done by 1820/14 = 130 men