13 men can do a piece of work in 20 days , all the 13 men started the work and after 10 days the number of men increased by 13 , then in how many days the remaining work will be done?
please give me the exact explanation please!!
Answers
Answered by
0
Answer:
Step-by-step explanation:
GIVEN,
NUMBER OF DAYS REQUIRED FOR 13 MEN TO DO WORK = 20 DAYS
NUMBER OF DAYS REQUIRED FOR 1 MAN TO DO WORK = 20/13 DAYS
SO,
EFFICIENCY OF 1 MAN = 13/20
SO,
EFFICIENCY OF 13 MEN = 169/20
SO,
A.T.Q.,
(169/20)*10 +
I HOPE YOU UNDERSTOOD THE QUESTION