Math, asked by mehak1332, 9 months ago

13 men can weave 117 baskets in a week .How many men will be needed to weave 189 baskets in 3 days (direct and indirect variation chapter)I WANT ANSWER WITH FULL EXPLANATION

Answers

Answered by amm201178
1

Answer:

Theerefore th number of men required is 49.

Step-by-step explanation:

Let the work done by each man per day be x.

 

It is given that 13 men can weave 117 baskets in a week = 7 days.

 

13x × 7 = 117

Therefore x = 9/7

 

Now, the number of men required to weave 189 baskests in 3 days be m.

Therefore,

ym × 3 = 189

y  = 63/m = 63  ÷ (9/7) = 49

Theerefore th number of men required is 49.